Sediment Removal

Sediment build up creates cloudy water and over time blocks essential light to water plants that create a healthy environment below the water line

Sediment Removal

Giant diggers, boats and a whole load of mud. Find out more about how we cleared the Broad!

Water bure

Sediment Removal: Science Officer Overview

Read our science officer overview on sediment removal.

Starting in autumn 2016, 55,000 cubic meters of soft sediment will be removed from the bottom of Hoveton Great Broad – that’s the equivalent of 22 Olympic-sized swimming pools. The sediment will be re-used within the lake to re-shape the banks to create new land habitats for plants birds and insects, reducing the cost and environmental impact of having to dispose of the sediment elsewhere.

Sediment will be dug from the bed of the broad by diggers on floating rafts. *

It will then be pumped into long tubes made of geotextile material to create artificial banks.

These will be used to re-shape the banks of the broad. More sediment will then be pumped behind these banks to create new land upon which reeds and other wetland plants will grow.

To kick-start this growth, plants will be taken from other parts of Bure Marshes National Nature Reserve and laid on top of the newly-created banks.

From there, the vegetation will naturally spread across the newly-created land.

This technique has already been successfully used by the Broads Authority at near-by Salhouse Broad.

Sediment removal will increase the average depth of the broad to 1.1m – just longer than a swan’s neck, so they can’t reach down and eat the new shoots of young water plants. This will also reduce the effects of wind and waves on the sediment, so it won’t move about as much, giving new water plants more stable and sturdy ground to grow in.

By reusing the sediment, we won’t need to send any material to landfill, which would have required 1,750 lorry trips!

Works are scheduled to take place over two phases; winter 2016 – 2017 and then again in winter 2017 – 2018.

* Images reproduced by kind permission of Netics.

This site uses cookies to store information about your computer.

Some of these cookies are essential, while others help us to improve your experience by providing insights into how the site is being used. For more detailed information on the cookies we use, please check our Cookie Policy.

Cookies

Strictly Necessary

These cookies are necessary for the website to function and cannot be switched off in our systems. They are usually only set in response to actions made by you which amount to a request for services, such as setting your privacy preferences, logging in or filling in forms. You can set your browser to block or alert you about these cookies, but some parts of the site may not work then. For more detailed information on the cookies we use, please check our Cookie Policy.

Functional / Essential

Functionality cookies allow websites to remember the user’s site preferences and choices they make on the site when using features such maps. Functionality cookies can include first party, third party, persistent or session cookies. Similar to strictly necessary cookies, functionality cookies are used to provide a service on the website.

Analytics

These cookies allow us to count visits and traffic sources, so we can measure and improve the performance of our site. They help us know which pages are the most and least popular and see how visitors move around the site. All information these cookies collect is aggregated and therefore anonymous. If you do not allow these cookies, we will not know when you have visited our site.

Powered by the GRIT Cookie Controller